136 Kitchener Road - Waiuku - Auckland | info@lscivil.co.nz
INCOMING DUCT
- Excavations. Laying of new ducting for proposed substation build.
SEWER UPGRADE
- Install new sanitary sewer from new substation to existing Watercare sewer manhole located down Kitchener Rd.
DEMOLITION
- Demo of existing substation building and removal of off-site.
CIVIL
- Demo of existing switch-yard. Installation of transformer foundations with precast walls. Oils SEPA installation. Precast ducting. Carpark, drainage, fencing and security fencing.
STAGE 1 - bulk earthworks, duct installation, retaining walls and drainage.